“Global High Tech Media” Company

“Global High Tech Media” Company

Case Studies/Data Center Decommissioning

Decommissioning a 400,000 SF Manhattan data center

A global high-tech information company relocating off West Street needed its 15 MW data center dismantled and its assets monetized. Quantum ran a 30–40-person crew and recovered everything from 667,200 lbs of batteries to 1,800 data cabinets — returning substantial revenue.

Large Manhattan data center decommissioning by Quantum Technology

Client
Global High-Tech Info Co.Name withheld by policy
Location
Manhattan, New York
Timeline
3 Months30–40-person crew
Result
Substantial RevenueReturned to the client

The Challenge

A giant Manhattan facility, on a lease clock

A global high-tech information company decided to relocate its 400,000 square foot data center on West Street in Manhattan to Orangeburg, NY. The company’s lease required it to dismantle and remove almost all of the infrastructure that supported the old data center.

On recommendations from several different sources, the company engaged Quantum Technology to execute the decommission and monetize the assets. (The company’s privacy policy restricts advertising its name, but it will provide a reference and recommendation of Quantum upon request.)

Inside the Manhattan data center

By the Numbers

The scale of the site

Facility
400,000 SFData center
Power
15 MWFacility capacity
Cabinets
1,800Data cabinets removed
UPS
27Liebert UPS systems

Battery and feeder removal at the Manhattan data center
The Approach

De-energize, verify, dismantle, recover

Quantum was responsible for the de-energization and verification of the electrical systems — safe-off, lock and tag out — before any removal began. A 30–40-person crew then worked through the facility, decommissioning, removing and selling or recycling the full build-out.

That included 1,680 jars of wet-cell lead-acid batteries with their disconnects and racking, hundreds of thousands of pounds of feeder cable, 92 Liebert PDUs, 27 Liebert UPS systems, switchgear lineups and breaker cabinets, DC plants and rectifiers, 1,800 data cabinets, and hundreds of thousands of pounds of steel scrap.

667,200 lbsOf batteries recovered & recycled

The site held 1,680 jars — 667,200 lbs — of wet-cell lead-acid batteries, all removed with their disconnects and racking and routed to recycling.

What We Recovered

Removed, sold or recycled

A full-facility decommission, measured in tons.

✓1,680 jars (667,200 lbs) of wet-cell batteries, disconnects & racking
✓541,981 lbs of feeder cabling & wire
✓92 Liebert PDUs & 27 Liebert UPS systems
✓Switchgear lineups, breaker cabinets & panels
✓DC plants, rectifiers & office furniture
✓1,800 data cabinets & several thousand PDU strips
✓295,240 lbs of steel scrap
✓De-energization, verification, lock & tag out

The Outcome

A clean exit and real money back

The lease obligation was met, the assets were monetized, and the client came away with substantial revenue.

Substantial revenue returned

By monetizing the assets rather than scrapping them, the decommission handed the client substantial revenue.

Handled safely at scale

A 30–40-person crew de-energized, verified and removed a 15 MW facility — including 667,200 lbs of batteries.

Lease obligation met

Almost all of the supporting infrastructure was removed, satisfying the West Street lease so the relocation could close out.

On Site

From the project

Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo
Global high-tech data center project photo

Your project could be next

Relocating or retiring a large data center?

We take on full-scale, multi-megawatt decommissions — de-energizing safely, meeting lease deadlines, and turning the assets into revenue instead of cost.

Fiserv

Fiserv

Case Studies/Data Center Decommissioning

A Market Street data center, back to original

Quantum won the bid to decommission Fiserv’s data center in downtown Philadelphia — 125 server racks and 60,000 SF of raised floor — coming in well below the trades by monetizing the assets, and returning the space to original condition.

Fiserv data center decommissioning in Philadelphia by Quantum Technology

Client
Fiserv
Location
Philadelphia, Pennsylvania
Timeline
6 WeeksDecommission & interior demo
Result
Back to OriginalAt less than the trades’ price

The Challenge

A competitive bid in a live building

Quantum Technology was invited to a walk-through, alongside various Philadelphia trades, to bid on the decommission of Fiserv’s data center on Market Street in Philadelphia. The equipment was quite old and didn’t carry strong resale value, so like the other bidders Quantum submitted a charge for the clean-out and interior demolition — but because of its ability to monetize the assets, that charge came in significantly lower than the trades.

The site had real complications: layers upon layers of cabling beneath the floor, much of it set in place by earlier tenants, with many connections that reached into other suites in the building.

Fiserv data center before decommissioning

Raised floor and cabling removal at Fiserv
The Approach

Careful work around an occupied building

Because the cabling tied into other suites, Quantum worked closely with the building electricians to untangle the connections safely, and with the building mechanics to make sure no leaking occurred during the removal of the CRAC units.

The demolition and recovery covered 125 server racks, 60,000 square feet of raised floor, cabling, piping, CRAC units, PDUs, fire suppression tanks, cubicles and partition walls — with the racks, PDUs, UPSs and raised floor resold, and the batteries, drywall, cabling and conduit recycled.

60,000 SFOf raised floor removed

Across 60,000 square feet of raised floor, Quantum pulled 125 server racks and the full power and cooling plant — returning the space to its original condition.

What We Removed

Data center and interior, together

Technical infrastructure and interior build-out, recovered and recycled.

✓125 server racks — resold
✓60,000 SF of raised floor — resold
✓CRAC units, PDUs & UPSs
✓UPS batteries — recycled
✓Fire suppression tanks, cabling & piping
✓Cubicles & non-load-bearing partition walls

The Outcome

Lower cost, clean finish, lasting relationship

The space came back to original condition, the price beat the trades, and Fiserv kept calling.

Below the trades’ price

By monetizing the assets, Quantum’s bid came in significantly lower than the other Philadelphia trades.

No disruption to neighbors

Working with the building’s electricians and mechanics, the crew untangled shared cabling and removed CRAC units without leaks.

A client for the long haul

Fiserv was extremely pleased and went on to hire Quantum for many more projects around the country.

On Site

From the project

Fiserv data center project photo
Fiserv data center project photo
Fiserv data center project photo
Fiserv data center project photo
Fiserv data center project photo
Fiserv data center project photo
Fiserv data center project photo
Fiserv data center project photo

Your project could be next

Getting bids on a decommission?

Because we recover and resell the assets, our number often comes in below the trades — and we work cleanly around occupied, shared buildings.

Lincoln Properties – Sungard Data Center

Lincoln Properties – Sungard Data Center

Case Studies/Data Center Decommissioning

Clearing a data center eight floors up

On the 8th floor of a busy downtown Philadelphia office building, Quantum decommissioned and liquidated a former SunGard data center — hundreds of cabinets, all the electrical and cooling, and the raised floor — handing the space back bare and broom-swept.

Former SunGard data center decommissioning in downtown Philadelphia by Quantum Technology

Client
Lincoln Properties
Location
Philadelphia, Pennsylvania
Timeline
3 WeeksDecommission & liquidation
Result
No Cost to OwnerAssets purchased, labor free

The Challenge

A high-rise data center to retire

Lincoln Harris Corporate Services Group hired Quantum Technology to decommission and liquidate a former SunGard data center on the 8th floor of a busy downtown Philadelphia office building — a working high-rise, with all the access and logistics that implies.

The brief was comprehensive: remove hundreds of data cabinets and all the electrical and cooling infrastructure, pull the raised floor, and leave the space in bare-walls, bare-floor, broom-swept condition.

Inside the former SunGard data center

The Approach

Bought the assets, covered the labor

The assets included several Eaton Powerware UPS systems, switchgear, transformers and CRAC units, several hundred data server cabinets, the raised floor and all the piping and cabling beneath it. Quantum purchased the assets from Lincoln and provided all of the labor at no charge — a profitable transaction for both parties. After the data center work was complete, Quantum went on to buy equipment stored in the building’s basement, including large breakers left behind by Digital Realty and huge fans.

HundredsOf data cabinets removed

Several hundred data server cabinets — plus UPS, switchgear, transformers, CRAC units and the raised floor — were removed and the space handed back broom-swept.

What We Removed

The full data center, floor and all

Every system came out — down to the piping and cabling beneath the raised floor.

✓Several hundred data server cabinets
✓Eaton Powerware UPS systems
✓Switchgear & transformers
✓CRAC cooling units
✓Raised floor, piping & cabling beneath
✓Space left bare & broom-swept

The Outcome

A clean floor and a deal that worked both ways

The space came back empty and swept, the owner paid nothing for the labor, and Quantum kept finding value in the building.

No cost to the owner

Quantum purchased the assets and provided all the labor at no charge — profitable for both sides.

Handed back broom-swept

Hundreds of cabinets, the UPS and cooling plant and the raised floor all came out, leaving bare walls and floor.

Value found beyond the floor

Quantum also purchased equipment stored in the basement — breakers and fans left behind over the years — for resale or recycling.

On Site

From the project

Lincoln SunGard data center project photo
Lincoln SunGard data center project photo
Lincoln SunGard data center project photo
Lincoln SunGard data center project photo
Lincoln SunGard data center project photo
Lincoln SunGard data center project photo
Lincoln SunGard data center project photo
Lincoln SunGard data center project photo

Your project could be next

Decommissioning in an occupied building?

We handle high-rise and downtown data center decommissions end to end — and where the assets justify it, we buy them and cover the labor, so the removal costs you nothing.

Viacom Data Center

Viacom Data Center

Case Studies/Data Center Decommissioning

Gutting a 107,000 SF data center — at no cost

CPR bought a former Viacom data center in Secaucus and needed it stripped back to a leasable shell. Quantum offered to do the whole job at no cost — paying for the work through the assets we recovered.

Former Viacom data center gutting in Secaucus, New Jersey by Quantum Technology

Client
CPR
Location
Secaucus, New Jersey
Timeline
6 WeeksGut & building prep
Result
No Cost to OwnerCovered by recovered assets

The Challenge

A 1980s data center, ready for its next life

In 1988, Viacom built a 107,000 square foot data center facility in Secaucus, New Jersey. The building was eventually purchased by CPR, a real estate investment company, who needed the data center gutted and the building brought back to a point where it could be repurposed and re-leased.

Quantum Technology offered to do the job at no cost to CPR — using the recovered assets to pay for the labor, trucking, warehousing, rentals, machinery, admin and insurance, and still turn a profit.

Inside the former Viacom data center

Electrical tracing and glycol recovery at the Viacom data center
The Approach

Trace it, drain it, tear it out

With no blueprints to work from — Viacom had layered the wiring over many years — Quantum’s electricians spent four days tracing every circuit before the disconnects could begin. Rather than call in a glycol tanker, the crew drained the huge glycol system into 255-gallon totes for refining and resale.

From there the crew tore out the entire data center — floors, ceiling, piping, cabling and equipment — and removed the brick and glass partition walls, draining and certifying the removal of an underground tank along the way.

107,000 SFData center gutted & recovered

A 107,000 square foot facility, stripped back to a leasable shell — with everything inside resold or recycled rather than sent to landfill.

Scope of Work

A full gut, inside and out

Technical infrastructure, structure and site — all handled by Quantum’s crews.

✓Removal of 3 generators, incl. two 13,200v Caterpillars
✓Full electrical trace & disconnect
✓Glycol system drained to totes for resale
✓Entire data center torn out — floors, ceiling, piping, cabling
✓Brick & glass partition wall removal
✓Underground tank drained & certified removed

In the client’s words

“You have a great talent where you can turn almost anything into money. I don’t know how you do it. I know how to buy properties and turn leases and sales into money. But I would love to learn how to do what you do.”

CheskyOwner, CPR

The Outcome

A leasable shell, paid for by its own assets

The building came back as a repurposable space, the equipment found new homes, and the relationship led to three more projects.

Done at no cost to CPR

The recovered assets covered the labor, trucking, warehousing and machinery — so the owner paid nothing out of pocket for the gut.

Everything resold or recycled

Dry coolers, UPSs, switchgear, cabinets, generators and glycol all went back into use rather than to landfill.

A relationship, not a one-off

The owner became a friend and a repeat client — Quantum went on to complete three more projects for him.

On Site

From the project

Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo
Viacom data center project photo

Your project could be next

Need a building stripped back to a shell?

We gut data centers down to leasable space — and where the assets justify it, we can do the work at no cost to you, paid for by what we recover.

Turner Construction for ASCO

Turner Construction for ASCO

Case Studies/Data Center Decommissioning

Buying and clearing a legacy data center

At the former AT&T Shannon Labs building in Florham Park, Quantum was invited in to purchase the assets and decommission the data center — UPS, cooling, Halon, 16,000 lbs of batteries and even the full company cafeteria.

Decommissioning the former AT&T Shannon Labs data center for Turner Construction and ASCO

Client
Turner Construction for ASCO
Location
Florham Park, New Jersey
Timeline
1 WeekAsset purchase & decommission
Result
Assets RecoveredPurchased & resold, not scrapped

The Challenge

A building changing hands, full of equipment

Turner Construction was carrying out an interior demolition of the old AT&T Shannon Labs building in Florham Park, New Jersey for Jones Lang LaSalle, who had just sold it to ASCO — the world’s leading manufacturer of power transfer switches.

The building still held a working data center and a full company cafeteria. Quantum Technology was invited in to purchase the assets and decommission the data center equipment so the demolition could move forward.

Data center equipment at the former AT&T Shannon Labs building

The Approach

Purchased, decommissioned, resold

Rather than simply hauling equipment out, Quantum purchased and resold the UPS equipment, Liebert air conditioners, PDUs, transformers, fire suppressant and the cafeteria equipment — recovering value from assets that would otherwise have been scrapped. Hazardous items were handled by trained technicians: Halon detonators were safely deactivated and the Halon recycled, and the sealed lead-acid batteries were removed by crews in Arc Flash suits using insulated tools and mats.

16,000 lbsOf batteries safely removed

Strung in series, sealed lead-acid batteries carry enough voltage to burn, break bones or kill. Quantum’s trained technicians removed 16,000 lbs of batteries in Arc Flash suits with insulated tools — the way this work has to be done.

What We Handled

Data center and facility assets

A single crew cleared the technical infrastructure and the building services around it.

✓UPS systems disconnect & removal
✓Liebert air conditioners & CRAC units
✓Halon tanks — safe deactivation & recycling
✓16,000 lbs of sealed lead-acid batteries
✓PDUs, transformers & fire suppression
✓Commercial cafeteria & kitchen equipment

The Outcome

Value recovered, demolition unblocked

The data center and facility assets came out safely, found a second home, and cleared the way for Turner’s demolition.

Assets bought and resold

UPS equipment, Liebert units, PDUs, transformers, fire suppression and cafeteria gear were purchased and resold rather than scrapped.

Hazards handled by the book

Halon was deactivated and recycled, and 16,000 lbs of batteries were removed by crews in Arc Flash suits with insulated tools.

Demolition kept on track

With the data center cleared, Turner Construction’s interior demolition could move ahead on schedule.

On Site

From the project

Turner ASCO project photo
Turner ASCO project photo
Turner ASCO project photo
Turner ASCO project photo
Turner ASCO project photo
Turner ASCO project photo
Turner ASCO project photo
Turner ASCO project photo

Your project could be next

Clearing a building before demolition?

We buy and decommission data center and facility assets — UPS, cooling, Halon, batteries, even cafeteria equipment — handling the hazards safely and recovering the value.