Magnolia Investment Partners

Magnolia Investment Partners

Case Studies/Data Center Decommissioning

A Nashville data center, fully recovered

On Burton Hills Blvd in Nashville, Quantum decommissioned Magnolia Investment Partners’ data center — raised floor, cooling, UPS and a 600kW generator — and hauled every piece back to our warehouses for refurbishment and resale.

Magnolia Investment Partners data center decommissioning by Quantum Technology

Client
Magnolia Investment Partners
Location
Nashville, Tennessee
Timeline
2 WeeksFull decommission
Result
Fully RecoveredEquipment bound for refurb & resale

The Project

A compact data center, cleared out completely

In July 2022, Quantum Technology completed a data center decommissioning at 10 Burton Hills Blvd in Nashville, Tennessee for Magnolia Investment Partners, with a thank-you to Avison Young for the introduction.

The data center consisted of approximately 2,000 SF of raised floor, 200 tons of cooling, 200kW of UPS, a 600kW generator and all of the related equipment. Quantum brought all of the equipment back to its warehouses in Shippensburg, PA for refurbishing and resale.

2,000 SFOf raised floor decommissioned

Around 2,000 square feet of raised floor — plus the cooling, UPS and generator beneath it — was decommissioned and recovered for a second life.

What We Removed

The full data center stack

Every major system was disconnected, removed and recovered.

✓~2,000 SF of raised floor
✓200 tons of cooling
✓200kW of UPS
✓600kW generator & all related equipment

The Outcome

Cleared, recovered, and resold

The facility was fully decommissioned and every system routed back into productive use.

The whole stack removed

Raised floor, cooling, UPS and generator were all disconnected and removed in a single two-week window.

Equipment recovered for reuse

All of the equipment was brought back to Quantum’s Shippensburg warehouses for refurbishing and resale.

A smooth, referred engagement

Introduced by Avison Young, the project wrapped cleanly for the team at Magnolia Investment Partners.

Your project could be next

Retiring a data center?

Raised floor, cooling, UPS, generators — we remove the full stack and recover its value through refurbishment and resale.

Lifenet Health

Lifenet Health

Case Studies/Data Center Decommissioning

A full data center decommission with zero waste

For Lifenet Health, Quantum handled every phase — from electrical shutdown and tag out to rooftop condenser removal and full infrastructure teardown — and sent every material to resale or recycling, generating no waste.

Lifenet Health data center decommissioning by Quantum Technology

Client
Lifenet Health
Location
Virginia
Timeline
2 WeeksAll phases
Result
Zero WasteAll materials resold or recycled

The Project

Every phase, handled by one crew

Lifenet Health is a non-profit global leader in regenerative medicine and the world’s largest provider of allograft bio-implants and organs for transplantation. In July 2022, Quantum completed a full data center decommissioning at its facility in Virginia.

Quantum handled all phases of the project — from electrical shutdown and tag out to freon recovery, rooftop removal of the condenser farm, and the disconnect and removal of all data center infrastructure. Every material was routed to resale or recycling, so the project generated no waste.

100%Of materials resold or recycled

Every material pulled from the facility was re-sold or recycled — no waste was generated on the project.

Scope of Work

All phases of the decommission

A single Quantum crew carried the project from power-down to final removal.

✓Electrical shutdown & tag out
✓Freon recovery
✓Rooftop condenser farm removal
✓Disconnect & removal of all data center infrastructure

In the client’s words

“It was a pleasure working with Jose (Quantum’s foreman) and his team, they were professional and didn’t mind going the extra mile to get the job done in a short timeframe. Thanks again.”

Kevin MurphySenior Project Manager, Lifenet Health

The Outcome

Cleared cleanly, with nothing wasted

The facility was fully decommissioned on a short timeline, with every material put back into use or recycled.

Every phase in-house

From electrical shutdown and tag out through rooftop condenser removal, one crew carried the whole project.

No waste generated

All materials were re-sold or recycled — nothing from the project went to landfill.

Done on a short timeline

The client credited the crew with going the extra mile to complete the work in a short timeframe.

Your project could be next

Decommissioning a data center?

We handle every phase — power-down, refrigerant recovery, rooftop equipment, and full infrastructure removal — and keep materials out of the landfill through resale and recycling.

Former Michigan Consolidated Gas Company Data Center

Former Michigan Consolidated Gas Company Data Center

Case Studies/Data Center Decommissioning

Turning a shuttered data center back into cash

A 72,866-square-foot data center in Dearborn had sat dark since 1997. Quantum decommissioned and resold its infrastructure for Holding Source LLC — recovering several hundred thousand dollars in asset value and clearing the way for redevelopment.

Michigan Consolidated Gas data center decommissioning by Quantum Technology

Client
Holding Source LLC
Location
Dearborn, Michigan
Timeline
2 WeeksFull data center decommission
Result
Six-Figure RecoveryHundreds of thousands in asset value

The Challenge

A legacy data center standing in the way of redevelopment

Built by MichCon in 1982 and upgraded in 1994, the 72,866-square-foot data center at 5225 Auto Club Drive was shuttered in 1997. The legacy facility was eventually sold to Holding Source LLC — a major Dearborn developer — with plans to redevelop the property.

Before redevelopment could move forward, the aging infrastructure had to come out: chillers and cooling towers, pad mount transformers, indoor and outdoor switchgear and substations, a generator, ATS’s, pumps, motors, motor controls, UPS systems, PDUs, CRACs and electrical panels. The goal wasn’t just removal — it was recovering as much value as possible for the owner.

Michigan Consolidated data center equipment before decommissioning

Our Approach

Decommission, recover, resell

Quantum’s mission was to create several hundred thousand dollars of cash for Holding Source by decommissioning the data center and reselling its assets. In two weeks, crews removed the full mechanical and electrical plant and routed it into Quantum’s resale pipeline.

The timing played to a strength Quantum had recently built a division around: hard-to-acquire switchgear, electrical panels and pad mount transformers. Post-Covid supply-chain constraints had pushed lead times and prices sky-high, and Quantum stepped in to fill the gap — inventorying recovered equipment across its Shippensburg and Philadelphia warehouses and offering it to companies nationwide at competitive prices, putting infrastructure back into productive use.

Quantum Technology crew decommissioning the data center
72,866 SFData center decommissioned

Built in 1982 and dark since 1997, the 72,866-square-foot facility was fully decommissioned in two weeks — its infrastructure recovered for resale rather than scrapped.

Scope of Work

The full mechanical and electrical plant

Quantum removed and recovered the data center’s complete infrastructure, from cooling to switchgear.

✓Chillers & cooling towers
✓Pad mount transformers
✓Indoor & outdoor switchgear & substations
✓Generator, ATS’s, pumps & motors
✓Motor controls & UPS systems
✓PDUs, CRACs & electrical panels

The Outcome

Cash recovered, redevelopment unlocked

The shuttered facility’s infrastructure was turned into six figures of value for the owner and routed back into productive use.

Several hundred thousand dollars recovered

Quantum’s decommission and resale turned the shuttered data center’s assets into six figures of cash for Holding Source.

Hard-to-source gear back in service

Switchgear, electrical panels and pad mount transformers — items with long post-Covid lead times — were recovered and offered for resale nationwide.

A clear path to redevelopment

With the infrastructure removed, the legacy facility was ready for Holding Source’s redevelopment plans.

On Site

Inside the Michigan Consolidated decommission

A look at the crews, rigging, and equipment that came out of the facility.

Michigan Consolidated decommissioning photoMichigan Consolidated decommissioning photoMichigan Consolidated decommissioning photoMichigan Consolidated decommissioning photoMichigan Consolidated decommissioning photoMichigan Consolidated decommissioning photo

Your project could be next

Decommissioning a data center?

Tell us what’s on the floor. We’ll decommission the facility, recover the switchgear, transformers and mechanical plant, and show you the value we can put back in your pocket.

BASF Data Center

BASF Data Center

Case Studies/Data Center Decommissioning

Recovering a full electrical infrastructure, ahead of demolition

Before a long-vacant BASF campus in Mount Olive came down to make way for a 600,000 SF distribution center, Quantum purchased and removed the complete electrical infrastructure from four buildings — including an 11,000 lb substation lifted out through the Penthouse roof.

BASF data center electrical infrastructure removal by Quantum Technology

Client
Bromag
Location
Mount Olive, New Jersey
Timeline
3 WeeksFour-building electrical recovery
Result
Assets RecoveredElectrical infrastructure removed & resold

The Challenge

A 30-year-vacant campus, about to come down

BASF’s five-building Mount Olive campus once housed 3,000 employees. After the company moved its headquarters to East Hanover, the site sat vacant for nearly 30 years — and it’s now being demolished to make way for a 600,000-square-foot distribution center.

Before the buildings came down, the valuable electrical infrastructure inside had to come out. Quantum’s scope spanned four of the buildings: disconnect, rig, remove, and transport the bulk of the equipment — including, most challenging of all, an 11,000-pound substation that had to come out through the roof of the Penthouse.

BASF campus electrical equipment before removal

Our Approach

Purchase, disconnect, rig, recover

Quantum signed a contract with Bromag, the New Jersey demolition company handling the teardown, to purchase and remove the complete electrical infrastructure. Across four buildings, Quantum’s crews disconnected, rigged, and removed the equipment, then transported the bulk of it back to the company’s 200,000-square-foot warehouse.

It’s a model Quantum runs alongside its own demolition and full-scale data center decommissions: working with demo companies and owners to monetize electrical and mechanical assets — buying them, handling the disconnect and removal, then shipping them to its Shippensburg and Philadelphia warehouses to be refurbished and resold. Quantum currently stocks over 80,000 pieces of equipment and has completed well over 4,000 projects.

Quantum Technology crew removing electrical infrastructure
11,000 lbsSubstation removed through the roof

The most demanding lift of the project: an 11,000-pound substation that Quantum’s crew rigged out through the roof of the Penthouse and transported back to the warehouse.

Scope of Work

From contract to warehouse, handled in-house

Quantum purchased the assets and carried the full recovery itself — disconnect, rigging, removal, and transport across four buildings.

✓Purchase of the electrical assets
✓Disconnect across four buildings
✓Rigging & removal of bulk equipment
✓11,000 lb substation removal through the Penthouse roof
✓Transport to Quantum’s 200,000 SF warehouse
✓Refurbishment & resale on the used market

The Outcome

Infrastructure recovered, not scrapped

The electrical gear came out of four buildings ahead of the teardown and headed back to Quantum’s warehouses for a second life.

Complete electrical infrastructure recovered

Across four buildings, Quantum purchased and removed the full electrical infrastructure ahead of the campus demolition.

An 11,000 lb substation, rigged out cleanly

The crew’s most demanding lift came out through the roof of the Penthouse and was transported safely back to the warehouse.

Equipment given a second life

Rather than being scrapped, the recovered gear headed to Quantum’s Shippensburg and Philadelphia warehouses to be refurbished and resold.

On Site

Inside the BASF recovery

A look at the crews, rigging, and equipment that came out ahead of demolition.

BASF recovery photoBASF recovery photoBASF recovery photoBASF recovery photoBASF recovery photoBASF recovery photo

Your project could be next

Clearing a facility before demolition?

We’ll buy the electrical and mechanical assets, handle the disconnect and removal, and show you the recovery value against the removal cost — before the building comes down.

Moderne Glass

Moderne Glass

Case Studies/Data Center Decommissioning

Clearing an out-of-use data center, floor to ceiling

Quantum Technology was brought in to clear an out-of-use data center in Pennsylvania — a complete, floor-to-ceiling cleanout that included removing the two generators supporting the facility.

Moderne Glass data center decommissioning by Quantum Technology

Client
Tom McKnight
Location
Pennsylvania
Timeline
3 WeeksFull facility cleanout
Result
Full CleanoutFloor to ceiling

Project Overview

A complete floor-to-ceiling cleanout

Quantum Technology was hired to remove an out-of-use data center in Pennsylvania — a complete cleanout of the facility, floor to ceiling.

The scope included removing the two generators that had been supporting the facility.

Moderne Glass data center cleanout
2Generators removed

Alongside the full floor-to-ceiling cleanout, Quantum removed the two generators that had been supporting the facility.

Scope of Work

What the project covered

✓Complete floor-to-ceiling cleanout
✓Full data center decommissioning
✓Removal of 2 supporting generators

On Site

Inside the Moderne Glass cleanout

Moderne Glass cleanout photoModerne Glass cleanout photoModerne Glass cleanout photoModerne Glass cleanout photoModerne Glass cleanout photoModerne Glass cleanout photo

Your project could be next

Decommissioning a data center?

Tell us what’s on the floor. We’ll handle the full cleanout — equipment, generators, and all — and show you the recovery value against the removal cost.