Clearing the old AOL data center for a new one

To open in Ashburn, Infomart chose the former AOL data center and brought in DPR Construction. Quantum decommissioned 120,000+ SF — roughly 800,000 lbs of batteries, 96 CRAC units and a full chiller plant — over a 10-week, safety-first program.

Former AOL data center decommissioning in Ashburn, Virginia by Quantum Technology

Client
DPR Construction for Infomart
Location
Ashburn, Virginia
Timeline
10 Weeks30–40-member crew
Result
Cleared for Build-OutBecame a major Infomart DC

The Challenge

An old data center, in the way of a new one

When Infomart Data Centers, a national data center provider, wanted to open operations in Ashburn, Virginia, it identified the old AOL data center building as an ideal location and hired DPR Construction — a national construction firm booking around $4 billion in new builds a year — to handle the design and build-out.

DPR contracted with Quantum Technology to decommission the old data center and purchase the assets, dismantling the existing build-out, pulling all the feeders, and preparing the space for a brand-new data center build.

Inside the former AOL data center

By the Numbers

The scale of the site

Space
120,000+ SFData center space
Batteries
~800,000 lbsWet-cell lead-acid
Cooling
96 CRACUnits removed
UPS
15UPS systems

Decommissioning work inside the data center
The Approach

A big job, run on safety

A 30–40-member crew worked the site for about 10 weeks. Each day began with a pre-task checklist identifying the day’s tasks, crew assignments and possible hazards — with hazards called out by every member of each team to encourage full participation in a 100% safe working environment. Crews operated under OSHA regulations with forklift and fall-protection certification.

Beyond the equipment decommission, Quantum recycled roughly 328,000 lbs of non-ferrous metal and 443,000 lbs of scrap steel — purchasing the assets and keeping the recoverable material out of landfill.

~800,000 lbsOf batteries decommissioned

Three battery rooms held approximately 800,000 lbs of wet-cell lead-acid batteries — all removed and handled by trained, certified crews.

What We Removed

Six data centers’ worth of infrastructure

Power, cooling, batteries and structure — across the whole facility.

✓6 main data centers of 15,000 SF each
✓96 CRAC units
✓48 Cyberex PDUs & 168 RPPs
✓15 UPS systems & associated switchgear
✓~800,000 lbs of wet-cell batteries (3 battery rooms)
✓Chiller plant — 5 chillers & Inergen fire suppression
✓Electrical panels & server racks
✓328,000 lbs non-ferrous & 443,000 lbs steel recycled

The Outcome

Cleared, recovered, and reborn

The old facility came out cleanly and safely — and the building went on to a second life as a major data center.

A new data center was born

The client was extremely satisfied, and the former AOL building became a major data center for Infomart.

A 100% safe program

Daily pre-task hazard reviews and OSHA-certified crews kept a large, high-voltage decommission running safely.

Assets bought and recycled

Quantum purchased the assets and recycled hundreds of thousands of pounds of non-ferrous metal and steel.

On Site

From the project

Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo
Infomart data center project photo

Your project could be next

Repurposing a data center shell?

We clear existing facilities for new builds — power, cooling, batteries and all — on OSHA-certified, safety-first programs, and buy the assets to keep your costs down.

Skills

Posted on

October 16, 2026

Submit a Comment

Your email address will not be published. Required fields are marked *